Calculation Method of Tunnel Over-Under Excavation Based on Point Cloud Data

Journal Title: Urban Mass Transit - Year 2025, Vol 28, Issue 5

Abstract

[Objective] During tunnel construction using the drilling and blasting method, over-excavation and under-excavation issues are always unavoidable. To accurately identify over-under excavation positions and calculate the over-under excavation, an excavation calculation model based on tunnel longitudinal section lines is proposed for this issue. [Method] Point cloud data collected by the 3D laser scanner are pre-processed and the tunnel central axis is extracted. The 3D Delaunay algorithm is applied for curved surface reconstruction of point cloud data, and the transverse and longitudinal section lines are extracted on the curved surface. Over-under excavation areas are calculated by comparing actual cross-section profile lines with theoretical profile lines. Combined with cubic spline curve fitting results of longitudinal section lines, the over-under excavation areas per unit radius are obtained, thereby conducting analysis of the functional relationship between over-under excavation areas and tunnel mileage. [Result & Conclusion] Combining transverse section over-under excavation area with cubic spline curve fitting results of longitudinal section lines, and the method for calculating over-under excavation volumes by integrating along longitudinal section lines, the volume element changes along the tunnel mileage direction in terms of volume element shape are taken into account. The minimum unit of over-under excavation volumes is simplified into a curved prismoid, enabling over-under excavation volume calculation through integration. When applied to the actual tunnel over-under excavation analysis, under identical volume element division condition, the proposed calculation model demonstrates higher calculation accuracy than other calculation methods, while intuitively displaying tunnel over-under excavation situation through chromatograms and contour maps.

Authors and Affiliations

Zhipeng ZHANG, Wenming CHENG, Run DU, Hetian CHEN

Keywords

Related Articles

Fracture Cause Analysis and Treatment Effect for Urban Rail Transit Vibration Damping Track DI-type Elastic Strip

Objective Elastic strip is a critical component of rail vibration reduction fasteners, its mechanical performance and fatigue-load bearing capacity are crucial for urban rail transit train operational safety and track se...

Calculation Method for Heat Transfer Coefficient of Urban Rail Transit Aluminum-alloy Vehicle Enclosure Structure Based on Thermal Resistance Model

Objective According to the characteristics of urban rail transit aluminum-alloy vehicle enclosure structure,a K-value calculation method based on thermal resistance model is studied, thereby improving calculation accura...

Insulation Protection Tests and Safeguard Measures under Equipotential Connection of Platform Door and Steel Rails

Objective Under the equipotential connection method between platform door system and steel rail, once the ground insulation of the platform door system weakens, the discharge is prone to occur. In order to ensure passeng...

Mechanical Response Analysis of Mainline Tunnel Structures in the Full Process of Metro Shield Interval Connecting Passage Mechanical Construction

[Objective] The mechanical method construction of connecting passages significantly impacts the internal forces within the segment structures of metro mainline tunnels. It is essential to understand the force variation...

Analysis of Metro Flood Incidents During Operation and Suggestions for Emergency Management Informatization

Objective Once the metro flood incident occurs during operation, mild cases will cause train delay and even train suspension, while severe cases can result in property loss and worse, personal injury. Therefore, it is ne...

Download PDF file
  • EP ID EP766704
  • DOI 10.16037/j.1007-869x.2025.05.026
  • Views 11
  • Downloads 0

How To Cite

Zhipeng ZHANG, Wenming CHENG, Run DU, Hetian CHEN (2025). Calculation Method of Tunnel Over-Under Excavation Based on Point Cloud Data. Urban Mass Transit, 28(5), -. https://europub.co.uk/articles/-A-766704