Factory Downtime Minimization through Tracking of Maintenance Information System of Metahara Sugar Factory, Ethiopia

Journal Title: STAR Journal - Year 2014, Vol 3, Issue 3

Abstract

Analysis of factory downtime records of Metahara Sugar Factory for the past twelve consecutive years show that the total number of stops and stop hours of one of the stations (front factory) was more than 300% higher than other stations. The front factory comprises two tandems: tandem A and B. The total downtime records for the first six months of 2013/14 sugar production season for tandem A show that the downtime was mainly due to mechanical failures, lack of canes, preventive maintenance activities, cleanings due to blockages, and electrical failures, which account 64.1, 13.7, 6.8, 5.9 and 3.1 % of the total stop hours respectively. Similarly, the records for tandem B show that 64.2, 11.3, 8.7, 8.4 and 6.2 % of the total downtime were mainly due to mechanical failures, cleanings due to blockages, electrical failures, lack of canes and preventive maintenance activities respectively. Therefore, measures should be taken at the front factory to reduce mechanical failures and blockages in order to sustain the achievements of the factory. The factory sets to maintain factory downtime below 9% and total downtime below 12% but actual figures were higher. Factory downtime record for the first six months of 2013/14 sugar season showed reduction of 75.7%. But the overall achievements were still higher than the set values. In this paper, based on downtime records, it is believed that measures should be taken at the front factory in order to reduce mechanical failures and blockages. Only by considering lost production capability, an increase in annual sugar production capability of 78,705 quintals will be achieve (additional revenue of more than 4 millions USD annually).

Authors and Affiliations

Minale Getachew| Research and Training, Sugar Technology Research Directorate, Ethiopian Sugar Corporation, Post Box No: 15, Ethiopia

Keywords

Related Articles

Hydro Geophysical Investigation of Shebe Watershed, Jimma, South Western Ethiopia

The need to prospect for additional ground water sources in Shebe watershed, Jimma, Shebe town water supply became inevitable because of the fact that the existed water supply and the quality of the water with current...

Morphometric Analysis of Didessa River Catchment in Blue Nile Basin, Western Ethiopia

In the present paper an attempt has been made to study the morphometric characteristics of Didessa catchment which is part of Blue Nile River basin located in South Western part of Ethiopia. The study focused on evalua...

Global Epidemiology of Tuberculosis: Past, Present and Future

Tuberculosis (TB), one of the most widespread infectious diseases, is the leading cause of death in the world and has been known in humans since ancient time. The epidemiological trends of tuberculosis since the pre-chem...

Teachers’ Perceptions and Practices of Active Learning in Haramaya University, Eastern Ethiopia: The Case of Faculty of Education

The purpose of this study was to investigate instructors’ perceptions and practices of active learning, assess the extent to which instructors’ perceptions influence their practices and identify factors affecting t...

Download PDF file
  • EP ID EP9697
  • DOI http://dx.doi.org/10.4314/star.v3i3.24
  • Views 340
  • Downloads 17

How To Cite

Minale Getachew (2014). Factory Downtime Minimization through Tracking of Maintenance Information System of Metahara Sugar Factory, Ethiopia. STAR Journal, 3(3), 142-146. https://europub.co.uk/articles/-A-9697