Grouting Reinforcement Method and Application for Existing Piles in Open-excavation Tunnel Under-passing Bridge Engineering

Journal Title: Urban Mass Transit - Year 2024, Vol 27, Issue 7

Abstract

Objective When constructing a new tunnel under-passing bridge with open-excavation method, it is crucial to protect the existing pile foundation system within the excavation pit. In the project of South Hubin Road Tunnel under-passing Guangqing Highway Bridge, the foundation pit excavation leads to the exposure of existing bridge piles, affecting the bridge overall stiffness and causing pier settlement. Grouting reinforcement is proposed to stabilize the pit bottom and the pile surrounding. It is aimed to investigate the impact of variation in the grouting reinforcement range (thickness and width) on bridge deformation. Method Using finite element software Midas GTS for three-dimensional modeling, the bridge pier top displacement and the axial force distribution along the pile shafts are compared under different grouting reinforcement ranges. The impact of changes in grouting reinforcement width and thickness around the piles on bridge deformation, and the effect of improving pile bearing capacity are analyzed. Based on numerical calculation results and deformation control requirements, a construction reinforcement plan is formulated, and the pier abutment settlement is monitored on-site during tunnel construction. Result & Conclusion Grouting reinforcement around the piles can effectively compensate for the loss of friction pile side friction resistance, improving the load transfer efficiency in the reinforced section and better distributing the load from the superstructure. Increasing the thickness of reinforcement around the piles can significantly improve pier top settlement and differential settlement between adjacent piers. On-site monitoring of tunnel grouting reinforcement construction shows that both bridge settlement deformation and differential settlement meet the control requirements.

Authors and Affiliations

Haidong ZHANG

Keywords

Related Articles

Deformation Effect Analysis of Shield Tunnel Closely Side-passing Viaduct Pile Foundation

Objective Shield tunneling may cause displacement and deformation of the nearby viaduct foundation and reduce its bearing capacity. Therefore, the deformation effect caused by shield tunnel closely side-passing viaduct f...

Research on City Railway Train Driver Braking Test Scheme

Objective As one of the core systems in urban trains, the braking system's performance determines vehicle operational safety. The driver braking test is an essential function of the braking system in city railway trains,...

Research on Intelligent Identification of Worker′s Unsafe Behavior in Urban Rail Transit Based on Convolutional Neural Network Algorithm

[Objective] Worker′s unsafe behavior is the fundamental factor in urban rail transit construction accidents. As the traditional management mode is insufficient in restraining the workers from the unsafe behavior, it is n...

Maintenance Strategy Optimization of Urban Rail Transit OCS Based on Intelligent Operation and Maintenance

Objective With the development of the intelligence technology and the building of intelligent operation and maintenance platform for urban rail transit overhead catenary/collector system (OCS), the operation and mainte...

Research on Backup System of Train Operation Control System Based on Vehicle to Vehicle Communication

Objective At present, represented by TACS(train autonomous control system)and based on vehicle to vehicle communication, the backup system of train operation control system is not perfect, and needs to be further discuss...

Download PDF file
  • EP ID EP742609
  • DOI 10.16037/j.1007-869x.2024.07.025
  • Views 14
  • Downloads 0

How To Cite

Haidong ZHANG (2024). Grouting Reinforcement Method and Application for Existing Piles in Open-excavation Tunnel Under-passing Bridge Engineering. Urban Mass Transit, 27(7), -. https://europub.co.uk/articles/-A-742609