Simplified Calculation Method for Existing Tunnel Settlement Caused by Shield Under-passing Based on Timoshenko-PasternakModel

Journal Title: Urban Mass Transit - Year 2024, Vol 27, Issue 10

Abstract

Objective It is aimed to tackle the inefficient accuracy of traditional Euler-Bernoulli beam and Winkler foundation model in calculating settlement induced by shield under-passing existing tunnels. Method Based on the Timoshenko beam theory and Pasternak foundation theory, the Timoshenko-Pasternak model, which simultaneously considers the soil shear effect and the tunnel overall shear deformation, is introduced. Settlement control equations for shield under-passing existing tunnels are derived and solved using finite difference method to obtain settlement calculation results. These results are then compared in detail with finite element numerical simulation solutions, actual engineering monitoring data, and theoretical solutions from traditional Euler-Bernoulli-Winkler model. Result & Conclusion Research results show that the Euler-Bernoulli-Winkler model tends to underestimate settlement values and overestimate settlement trough width and segment opening amount for existing tunnels. Additionally, it fails to calculate the segment misalignment amount of existing tunnels. In contrast, the calculation results from Timoshenko-Pasternak model are more consistent with the numerical simulation and actual monitoring values. The model can accurately estimate settlement, settlement trough width, and segment opening amounts for existing tunnels, and provides reliable calculation results for tunnel segment misalignment. The findings are of significant practical value, offering a reliable reference for engineeringapplications.

Authors and Affiliations

Liang WANG, Bintao PAN, Jie JIANG, Yihang LONG

Keywords

Related Articles

Application of New Intelligent Anti-flood Equipment Series in Underground Engineering

[Objective] Currently, frequent underground engineering flooding accidents tend to cause serious economic losses and casualties. In case of flooding, manual sealing methods such as temporarily stacking sandbags or manu...

Activation Method and Activation Circuit for Singapore MRT Thomson Line FAO Trains

Objective During the commissioning and operation process of activation circuit for FAO (fully automatic operation) trains, there are situations where the train cannot be activated, thereby affecting the operational order...

Research on Intelligent Operation and Maintenance Platform of Urban Rail Transit Communication Based on Multi-dimensional Collaborative Collection and Calculation Technology

Objective At present, in urban rail transit communication systems, there commonly exist the problems like the deficiencies of poor openness and difficult interconnection between the subsystems and low level of digitizati...

Flood Prevention System Construction and Innovative Equipment Application in Metro Engineering

Objective In recent years, extreme rainfall weather frequently causes urban flooding, leading to many cases of metro engineering project water disasters, significant economic losses and personnel casualties. It is essent...

Impact of Air-conditioning Systems on Metro Vehicle Interior Noise and Optimization Analysis

Objective Metro vehicle interior noise affects passenger comfort, with the air-conditioning system causing an undeniable impact. Therefore, it is necessary to study related issues to improve passenger’s riding experience...

Download PDF file
  • EP ID EP749207
  • DOI 10.16037/j.1007-869x.2024.10.004
  • Views 41
  • Downloads 0

How To Cite

Liang WANG, Bintao PAN, Jie JIANG, Yihang LONG (2024). Simplified Calculation Method for Existing Tunnel Settlement Caused by Shield Under-passing Based on Timoshenko-PasternakModel. Urban Mass Transit, 27(10), -. https://europub.co.uk/articles/-A-749207