Effect Analysis of Excavation and Unloading of Deep Foundation Pit in Soft Soil Stratum on Pile Foundation of Underground Station
Journal Title: Urban Mass Transit - Year 2024, Vol 27, Issue 6
Abstract
Objective In the excavation process of deep foundation pit of underground station in deep soft soil stratum, excavation and unloading of the overlying soil in the pit will obviously impact the previously constructed superlong pile foundation in the pit, threatening the structure stability and engineering safety. In order to explore the effects of large-scale deep foundation pit excavation and unloading on the pile group at the station foundation pit bottom, it is necessary to analyze the deformation law of the superlong pile under pressure. Method A numerical analysis software Midas GTS NX is used to establish a finite element numerical calculation model for the underground station S2 east end well and make the excavation simulation analysis. Based on a comparison of the on-site actual monitored data and the numerical calculation results, the deformation law of the pile group at the pit bottom affected by the foundation pit excavation is discussed. Result & Conclusion The results show that the pile area under tension increases with the deepening of excavation,both the maximum tension and the maximum pressure of the end well pile foundation are greater than the standard range. The vertical displacement of the pile foundation at the pit bottom continuously increases in the process of excavation. The largest pile displacement occurs at the farthest distance from the edge of the end well. In the later stage of excavation, as the incremental uplift of the pile foundation increases significantly, the vertical displacement of the pile top needs to be monitored in real time to prevent engineering accidents.
Authors and Affiliations
Yuhe LU, Haixing ZHU, Chunlin DING, Guiying LI
Cause Analysis and Rectification Measures of Chongqing Rail Transit Line 1 Low-frequency Train Oscillation
Objective To address the issue of low-frequency train oscillation on Chongqing Rail Transit Line 1 (hereinafter as ′Line 1′), it is necessary to analyze the causes of the oscillation and formulate appropriate rectificati...
Active Control Technology for Lift Wing Structure Motion in High-speed Railway EMU
[Objective] The lift wing structure of high-speed railway EMU (electric multiple units) can reduce the wheel-rail frictional resistance, thereby decreasing wheel wear. However, due to the complex and variable operating...
Influence Factors of Strata Deformation Response Induced by Shield Tunneling in Thick Silty Clay Layer
[Objective] In thick silty clay layers, the disturbance caused by shield tunneling is affected by multiple factors such as strata conditions and construction parameters. Given the complexity of strata deformation, it is...
Analysis Model of Urban Rail Transit Service Quality Influencing Variable Factors Based on SEM
Objective Aiming to further enhance urban rail transit service with precision, it is essential to quantitatively extract the influencing variable factors of urban rail transit service quality and analyze the intrinsic re...
Land Subsidence Prediction Model of Rail Transit Based on High-frequency Combination Segment-Gene Expression Programming Algorithm
Objective Land subsidence prediction and control is one of the most concerned issues in rail transit shield tunnel construction. In order to solve the complex and poor interpretable problem of the model expression in the...