FEATURES OF DRILLING-AND-BLASTING AT CONSTRUCTION OF BESKIDSKIY TUNNEL

Journal Title: Наука та прогрес транспорту - Year 2016, Vol 0, Issue 5

Abstract

Purpose. In this article it is necessary to analyze the possibility of developing technology and increasing its efficiency during the Beskidskiy tunnel construction in difficult engineering and geological conditions. Methodology. The authors have performed analysis of the technological level of mining and construction works, new technique, equipment and production. One of the important issues of blasting operation is to ensure the seismic safety, acting at a distance of 30 m in the axes of single-track tunnel, as the distance to it will be 20 m from the nearest charge in the laying tunnel. This problem was solved by applying the combined blasting of blast-hole charges with delay-action and long-delay ways. Herewith the total mass of charges in the stope was divided into three groups, in which the first group is exploded by short-delay firing with, and the second one is exploded by short-delay firing too with intervals of 200…400 ms, the third is exploded by long-delay blasting at intervals of 500…10000 ms. The combined blasting of short-delay charges and delay action ones let significantly reduce seismic action at a mass explosion of charges when driving of double-track railway tunnel of a large cross-section. Findings. The paper presents the developed technology model, describing dependence of the machines from engineering and geological conditions. The methodology of drilling and blasting works at the construction of the tunnel callote and stross as well as a technique of arrangement determination and intervals of shot-delay and delay blasting of blasthole explosive charges was developed. Maximum permissible concentration of gases and vapours at blasting was presented. The calculations showed that the maximum level of gas contamination of the working area in Beskidskiy tunnel is achieved at blast operations. In accordance with this ventilation of the tunnel when driving is carried out by independent systems with mechanical ventilation by blowing using mine fans of special mining enterprises. Originality. The developed seismically safety charge masses are based on the well-known state about antiseismic blasting regulations. Practical value. The authors proposed and grounded the efficient technology for reduction to practice of drilling and blasting works (with dividing of the tunnel cross-section into the calotte and stross during of the Beskydy high-mountain tunnel construction. The results of technological experiment are presented.

Authors and Affiliations

V. D. Petrenko, O. L. Tiutkin, S. T. Proskurnia

Keywords

Related Articles

DEVELOPMENT, ESSENCE AND SCOPE OF APPLICATION OF STRUCTURAL AND CABLE-STAYED COMPOSITE STRUCTURES

Purpose. In construction there is a need to create new structures, including spatial coverage systems, the use of which will save materials and reduce the complexity of assembling processes and manufacturing. Summarizing...

THE SUBGRADE HETEROGENEITY CONSIDERATION OF A RAILWAY TRACK WHEN DETERMINING ITS STRESS-STRAIN STATE

Purpose. Increase of the speed and train carrying capacity causes the increase in the load on the railway track and, in turn, loads on the subgrade. This makes it necessary to clarify the calculation methods, both the up...

ON SURFACE FRACTURE OF RAIL HEADS

Purpose. The formation of crack-like defects in rails of railway tracks is a serious problem for engineering practice because of the danger of creating emergency situations. The purpose of this work is to establish theor...

ВЫБОР КОНСТРУКТИВНЫХ РЕШЕНИЙ ЭЛЕМЕНТОВ ВАГОНОВ С МАЛОЙ МАССОЙ ТАРЫ

Цель. В работе необходимо выявить причины существенно большего коэффициента тары вагонов колеи 1 520 мм в сравнении с грузовыми вагонами Северной Америки и дать рекомендации по снижению массы тары грузовых вагонов. Метод...

РАСЧЕТ ОПТИМАЛЬНЫХ ИНТЕРВАЛОВ ДЛЯ ВЫБОРА РЕЖИМОВ ВЗАИМОДЕЙСТВИЯ СТАНЦИЙ И ПУТЕЙ НЕОБЩЕГО ПОЛЬЗОВАНИЯ

Цель. Основной целью работы должно стать получение функциональных зависимостей для расчета оптимальных значений интервалов между подачами вагонов на фронты погрузки, выгрузки по критерию минимизации эксплуатационных затр...

Download PDF file
  • EP ID EP226354
  • DOI 10.15802/stp2016/84127
  • Views 91
  • Downloads 0

How To Cite

V. D. Petrenko, O. L. Tiutkin, S. T. Proskurnia (2016). FEATURES OF DRILLING-AND-BLASTING AT CONSTRUCTION OF BESKIDSKIY TUNNEL. Наука та прогрес транспорту, 0(5), 178-185. https://europub.co.uk/articles/-A-226354