Abstract

Objective Influence of metro tunnel closely under-passing the existing metro station and viaduct pile foundation is studied. Method Wulidun Station safety line tunnel on Hefei S1 Line closely under-passes the existing Wulidun Station on Metro Line 2. With this project as the background, the finite element software ABAQUS is used to build a three-dimensional model of the whole construction process, and the deformations of station structure and viaduct pile foundation under line by line excavation and simultaneous excavation of the above two lines are compared and analyzed. In order to investigate the applicability of similar engineering under different soil conditions, by changing the two parameters of soil cohesion and elastic modulus, the influence of the two parameters on the settlement of soil and station bottom plate during tunnel excavation are analyzed. Result & Conclusion After the completion of the tunnel excavation, the maximum settlements of the bottom plate of Metro Line 2 Wulidun Station under the two schemes are very similar being 0.73 mm and 0.77 mm, both meeting the requirements of the control standard. When the soil cohesion and elastic modulus are less than 70 kPa and 100 MPa respectively, the settlement of the station structure and the horizontal displacement of the pile foundation during tunnel excavation begin to increase significantly, which should be treated seriously.

Authors and Affiliations

Zhimin LI

Keywords

Related Articles

Preferable Stability Speed of Metro Vehicles Passing Steel Spring Floating Slab Tracks with Worn Wheels

[Objective] To enhance metro passenger riding experience, the speed range at which the carbody exhibits optimal stability while passing through tracks laid with floating slabs is explored. [Method] Using simulation softw...

Application Analysis of CTCS-3 in City Railway

Objective At present, there is still no practical case of using CTCS 3 (Chinese Train Control System Level 3) in city railway in China. The application of CTCS-3 system in city railway should be explored to expand its ap...

Simulation of Full-axle Steering Control Strategy for DRT

Objective Digital rail transit of rubber-tyred train (DRT) features a complex running structure with multiple carriages and axles, significantly differing from conventional rubber-tyred trains. Therefore, it is necessary...

Research on Urban Rail Transit Service Quality Evaluation Based on Passenger Demand

Objective Evaluation of urban rail transit service quality based on passenger demand not only promotes service quality improvement and enhances passenger satisfaction with travel, but also contributes to economic and soc...

Detection Method for Installation Effect of Switch Machine Movable/Static Contact Groups Based on Key Point Recognition

Objective Traditional methods for detecting the installation effect of SmMSC (switch machine movable/static contact) groups are slow, inaccurate, and susceptible to human errors. It is necessary to introduce a fast and h...

Download PDF file
  • EP ID EP737763
  • DOI 10.16037/j.1007-869x.2024.06.034
  • Views 23
  • Downloads 0

How To Cite

Zhimin LI (2024). Influence Analysis of Metro Tunnel Underground Construction on Existing Metro Station and Viaduct Pile Foundation. Urban Mass Transit, 27(6), -. https://europub.co.uk/articles/-A-737763