Abstract

Objective Many defects related to the lining of high -speed rail tunnels gradually become prominent with the increase of the high-speed rail construction completion years. The waterproof board cutting lining concrete is one of these serious defects. In order to reduce the structural disturbance and the above defects impact on line operation, new technologies need to be used to rectify the waterproof board cutting lining defects in the arch of high-speed rail tunnel. Method Based on a dual-line high-speed railway tunnel with a design speed of 200 km/h in southwest China, two adoptable treatment schemes (cast-in-place arch and lattice technology) after its arch waterproof board cutting the lining concrete are analyzed in detail. A comparative assessment of the safety and economy of the structure is also carried out. The construction organization, process flow, protective measures and construction effects of the defect rectification scheme using lattice technology are emphatically discussed. Result & Conclusion Compared with other schemes, the lattice technology rectification scheme makes full use of the existing structure bearing capacity, repairs the tunnel only in a local area with little impact on both the existing lining structures and the high-speed railway line operation. This scheme can significantly reduce the main stress and displacement of the structure, and make the bearing capacity of the defective lining meet the design requirements.

Authors and Affiliations

Lun GONG, Xingwang GONG, Lichuan WANG, Ming LIANG, Zhiqiang LIU, Yongjie FAN, Xuemin ZHANG

Keywords

Related Articles

Compatible Access of Multi-source Citizen Cards in Suzhou Urban Rail Transit Ticketing System

Objective To address the compatible access issue of other types of citizen card and ticket in ticketing system during urban rail transit operation, a unified planning on the compatible access of citizen cards within Suzh...

Stability Analysis of Jinan Qixiuchang Metro Station during the Foundation Pit Temporary Supports Dismantling

Objective It is prone to lose stability, affecting the engineering safety in the process of dismantling the supports for metro station deep and large foundation pit. Therefore, it is necessary to analyze the stability in...

Research on Traction Power Supply System for Shanghai Rail Transit Chongming Line

[Objective] It is to address issues such as stray current corrosion and limited distance for DC traction power supply systems conventionally using rail return in urban rail transit. [Method] After conducting a comparativ...

Structural Selection and Stress Analysis of Suzhou Rail Transit Column-free Stations

Objective In urban rail transit stations, a column-free structure is often adopted to create a spacious visual effect when the site is narrow or there is excess height. To achieve the goal of safety, reliability, and eco...

Turnout Design of Same-side Curved Track for Straddle Tourism Monorail

Objective The tourism rail project at a scenic area is a single-line route. To enhance tourists transportation efficiency, it is required to arrange two sets of single-opening curved track turnout symmetrically within th...

Download PDF file
  • EP ID EP744351
  • DOI 10.16037/j.1007-869x.2024.09.043
  • Views 64
  • Downloads 0

How To Cite

Lun GONG, Xingwang GONG, Lichuan WANG, Ming LIANG, Zhiqiang LIU, Yongjie FAN, Xuemin ZHANG (2024). Application of Lattice Technology in Defect Rectification for Waterproof Board Cutting Lining Concrete at High-speed RailwayTunnel Arch. Urban Mass Transit, 27(9), -. https://europub.co.uk/articles/-A-744351