Abstract

The construction disturbance of existing bridge piles traversed by interval subsurface excavation tunnel was analyzed by 3D numerical analysis and site measurement. The results show that the spatial effect of existing bridge piles displacement response is significant which caused by tunnel excavation. The subsidence difference value is caused by difference side pressure along piles. The piles displacements show S pattern on X axis,and the maximum value locates at top of pile. The displacement pattern is different with the tunnel axe on X axis. The piles displacements show parabola pattern on Y axis,and the maximum value locates at tunnel axes. The bending moment of existing bridge piles have two recurvature points,and the maximum value locates at tunnel axes. The bending moment of existing bridge piles is caused by different side pressure along piles.

Authors and Affiliations

Li HUANG, Xiaoyong LIANG, Xian LI

Keywords

Related Articles

Gray Relational Analysis of Red Mud Mass Fraction and Asphalt Performance

In order to analyze the variation trend and sensitivity of the asphalt performance index with the mass fraction of red mud changing, six kinds of non-dimensional treatment in the gray theory were used to obtain the effec...

Optimal Design of Braking Force Distribution Ratio of Biaxial Vehicles

The computational methods of synchronization adhesion coefficient,utilization adhesion coefficient and brake efficiency were determined according to the vehicle mechanical mode of car braking. The braking force distribut...

Analysis and Simulation of Steering Performance of Six-Wheeled Articulated Vehicle

A rear wheel steering six-wheeled swing-arm articulated vehicle was designed to improve the low space utilization of articulated vehicles during articulated steering. Meanwhile,a mechanical model for the steering of arti...

Performance Test of Aluminum Alloy Floor Formwork

The uniform load tests were carried out on a single aluminum alloy floor formwork and a model room composite aluminum alloy floor formwork system respectively, and the contrastive analysis was carried out.When the three...

Study on Leaf Epidermis Structure and Dust-retention Ability of Five Machilus Species

The seedling leaves of five Machilus species ( Machilus minkweiensis, Machilus parabreviflora, Machilus microcarpa, Machilus pauhoi, and Machilus yunnanensis) were taken as research objects.Morphological characteristics...

Download PDF file
  • EP ID EP477144
  • DOI 10.15926/j.cnki.issn1672-6871.2016.04.014
  • Views 57
  • Downloads 0

How To Cite

Li HUANG, Xiaoyong LIANG, Xian LI (2016). Construction Disturbance Analysis of Existing Bridge Piles Traversed by Interval Subsurface Excavation Tunnel. 河南科技大学学报(自然科学版), 37(4), 66-70. https://europub.co.uk/articles/-A-477144